The plant has been installed by Army
Welfare Trust. Construction of the Plant was started in 1993. Its first line of
the capacity of 2000 tones per day was complete and i started production in
1996. Erection/installation of second line also of the capacity 2000 tones per
day was started in 1997, commercial production started with effect from 1st July
2003. The plant was designed by M/s Tianjin Cement Design & Research institute,
China and was supplied by M/s China Building Material Industrial Corporation (CBMC)
and local Mechinery was manufactured by Heavy Mechanical Complex (HMC) Taxila,
Pakistan.
Total Capacity of the plant has been
enhanced by another 1000 tons per day, by which the capacity comes to 5000 tons
per day w.e.f. February 2006. |